About Bristar Non-Explosive Demolition Agent

Mixing of BRISTAR

I. Mixing Equipment:

Mix one bag (5 kg, 11 lb) of BRISTAR with water at a time by hand or preferably with a mechanical mixer. Prepare the following equipment.

(1) Container: For one bag of BRISTAR - a metal bucket or clean can of 10-20 liters capacity.

(2) Mixer: For instance, hand-mixer.

(3) Water meter: Breaker or measuring cylinder.

(4) Protection: Rubber gloves, safety goggles.

II. Mixing Method:

Pour approximately 1.5 liter (0.4 U.S. gallon) of water into container. Add one bag of BRISTAR gradually and mix well until it has a good fluidity.

When a viscosity of the mixture of BRISTAR and water is too high to pour into the hole, add a little water to get a good fluidity. Do not exceed 34% of water ratio (1.7 liter; 0.45 U.S. gallon per 5 kg; 11 lb. of BRISTAR). The mixing time by hand-mixer is about 2-3 minutes (it is recommended that mechanical mixer be used on large volume jobs). When mixing by hands, wear rubber gloves.

III. Mixing Water:

I. Use clean water, such as city water, river water, etc., i.e. not contaminated with oil, organic substances, etc.

II. Use the proper temperature of water for each grade of Bristar (refer to table 1 and figure 1)

III. Cool water below 15°C (59°F) must be used when the average atmospheric temperature is more than 30°C (86°F) for BRISTAR100.

IV. The cooler the water is, the longer BRISTAR will remain fluid.

Table I. BRISTAR designed for various range of temperature

TEMPERATURE RANGES
Product
Material Temperature
Range
Mixing Water
Temperature
Bristar 100

Bristar 150

Bristar 200

Bristar 300
59É to 95É F

50É to 68É F

41É to 59É F

23É to 41É F
59É

59É


50É

41É

*B-100, and B-200 used in this brochure indicate BRISTAR 100, 150, 200, and 300, respectively.

Fig. 1 Time required that expansive stress reaches 6000 t/m2 and Temperature

IV. Standard Quantity:

The quantity of BRISTAR to be used for cracking differs with the hole spaces and diameters. In Table 2, the relation between the quantity of BRISTAR used and the hole diameters is indicated for the hole of 1 m depth, where BRISTAR was mixed at a water ratio of 30%.

Table 2. Quantity of BRISTAR used per hole depth and the hole diameters.

Hole Diameter (mm) 36 38 40 42 44 46 48 50
BRISTAR (kg/m) 1.7 1.9 2.1 2.3 2.5 2.8 3.0 3.2
Hole Diameter (inch) 1 3/8 1 1/2 1 5/8 1 3/4 1 7/8 2
BRISTAR (lb/yd) 3.1 3.7 4.4 5.1 5.8 6.7

Filling of the hole with BRISTAR:

I. BRISTAR should be poured into holes within 10 minutes after mixing with water. BRISTAR may set up within 10 minutes losing its fluid properties and becoming difficult to pour. Once its fluidity is gone, it should not be diluted by re-mixing with water, as the strength is greatly reduced.

II. BRISTAR is best placed using a bucket with pour spout, coking gun or grouting pump, especially for a horizontal hole. Try to drill horizontal holes with some slope to help in filling.

III. BRISTAR must be poured into a hole to the brim.

IV. For a horizontal hole, the hole can be easily plugged with BRISTAR as it reaches a clay like consistency as it starts setting up. A slight slope makes their use much easier.

The average quantity of BRISTAR used per 1 m3 is 5kg for the material to be broken when working in virgin rock (8.4 lb/yd3). For fragmentation and reinforced concrete, an amount of 2 to 4 times of that is required. Design the hole diameter and the spacing by also referring to Table 3 or 'Hole Design for Rock' and 'Hole Design for Concrete' links (on the left) for specific needs.

Table 3: The formula to calculate Hole Diameter and amount of BRISTAR: LB/FT x Number of Holes x Depth of Holes‡44 (lbs.).

Hole Diameter   1 1/2" 1 5/8" 1 3/4" 1 7/8" 2"
SUPER
BRISTAR
2000
 
(lb/ft) no 1.8 2 2.2 no
(ft/bag) no 6.1 5.4 4.9 no
BRISTAR (lb/ft) 1.3 1.5 1.8 2 2.4
(ft/bag) 8.5 7.2 6.2 5.5 4.5
Note: The chart shows how many drilled feet one 11 lb. bag of BRISTAR yields. There are four 11 lb. bags per case. You may get 3% to 6% less due to field conditions like spilling and actual hole size.

Use of polyethylene sack in hole:

I. If there is water in the hole, place polyethylene thin sack equal to the hole diameter into the hole, insert a wooden rod into the bag and then fill BRISTAR into the sack. (See Fig. 2) The BRISTAR in the sack will displace the water in the hole. There is no change in the breaking effect by the use of this kind of sack.

II. When there are many joints or large voids in the material to be cracked or when BRISTAR somewhat leaks from the hole, use the sack.

III. When much water of the slurry is absorbed to the material to be cracked (for instance, a dry concrete), use the sack or spray water into the hole. In cold temperature, avoid the water sprayed freezing in the hole.

IV. When the material to be cracked is in water, use the sack indicated in Fig. 2. Try to use the bucket or the pump when filling into the pipe, remove it up, and then tie the sack to avoid BRISTAR filled diluting. If there is no flow of water around an entrance of the hole, BRISTAR may directly be poured into the hole using the pump and so on. It should gently displace the water in the hole.

Figure 2: Use of Polyethylene Sack in hole

After Treatment:

I. Tamping with mortar or sand is not required at all after the filling of BRISTAR. It is also not necessary to put on any restrictive cap. Just leave as it is and wait until crack initiates. Covering the filled hole with a plastic cover is desirable to avoid dilution of BRISTAR from external water source until cracking starts.

II. Spraying the surface with water after the cracks initiate tends to increase the width of cracks and speed the cracking process.





 

 

Demolition Technologies BRISTAR Distributors
P.O. Box 427
107 Mildred Street
Greenville, AL 36037
Phone: 1-800-282-4384
Fax: (334) 382-7548 
Email: info@demolitiontechnologies.com



 
About Bristar Non-Explosive Demolition Agent
Bristar Technical information
Properties Of BRISTAR
Fracture Mechanism
Test Breaking and Drilling
Mixing and Filling BRISTAR
Crack Formation Time
Container and Storage
BRISTAR Caution
Demolition Design for Rock
Demolition Design for Concrete
MSDS Sheet
BRISTAR Order Requests